Project Description Installation of Earthing Spiral plant & Shaft VGF Structure Area Ga-Maroga (Black Chrome Mine) Period In Progress Project Cost R473 264,30 Client Black Chrome Mine Reference Patric Sihlangu (Group Engineering Manager) (072 200 7211) The Final Output
Read MoreProject Description Repair Electrical motors Area Ga-Maroga (Black Chrome Mine) Period In Progress Project Cost R229 000 + Client Black Chrome Mine Reference Patric Sihlangu (Group Engineering Manager) (072 200 7211 The Final Output
Read MoreProject Description Construction of blast wall in substation Area Ga-Maroga (Black Chrome Mine) Period 4 Weeks Project Cost R205 400,00 Client Black Chrome Mine Reference Patric Sihlangu (Group Engineering Manager) (072 200 7211 The Final Output
Read MoreProject Description Storm water trench construction Area Ga-Maroga (Black Chrome Mine) Period 5 weeks Project Cost R164 000,00 Client Black Chrome Mine Reference Patric Sihlangu (Group Engineering Manager) (072 200 7211) The Final Output
Read MoreProject Description Infrared test on MCC and Substation Area Ga-Maroga (Black Chrome Mine) Period Two weeks Project Cost R164 000,00 Client Black Chrome Mine Reference Patric Sihlangu (Group Engineering Manager) (072 200 7211) The Final Output
Read MoreProject Description Wiring of main store office container Area Ga-Maroga (Black Chrome Mine) Period Once off Project Cost R36 400,00 Client Black Chrome Mine Reference Patric Sihlangu (Group Engineering Manager) (072 200 7211) The Final Output
Read MoreProject Description Erecting 690m of security fence Area Jane Furse, Limpopo Period 4 weeks Project Cost R328, 560.00 Client Mimed (PTY) LTD Reference Dr Michael Dzivhani (079 575 7937/ 013 492 1537) The Final Output